Staples Road Reconstruction Ph. 1 & 2 - Corpus Christi, TX

Client

City of Corpus Christi

RHSI Role

Construction Management & Inspection

RHSI was selected to carry out inspection services and construction management support for this project for reconstruction to one of the city's most highly traveled streets with limited disruption in traffic flow. Construction consisted of 10 inch concrete 70 ft. nominal back-to-back curbs with concrete sidewalks and associated pavement marking and signage improvements. The project also required 10,488 LF of storm water conduit improvements, 16,739 LF of waterline improvements, signalization improvements and temporary traffic control with an accelerated 18 month construction schedule (reduced from the original 24 months).