San Antonio Water System (SAWS) - Regional Carrizo Water Delivery Pipeline Project - Schertz, TX

Client

Maestas & Associates

RHSI Role

Construction Inspection

As a 3rd tier sub to Maestas & Associates and Black & Veatch, RHSI provided full time construction inspection services on this project. Beginning at the Schertz Parkway Pump Station, this project included the construction of approximately 60,000 LF of 36” potable water polyurethane coated steel transmission main pipeline and will extend to the SAWS Naco Pump Station. This line traverses 11 miles of urban and developed areas and required extensive coordination with utility companies and landowners, and included major crossings of I-35, Loop 1604, Union Pacific Railroad and Cibolo Creek. RHSI inspectors worked alongside SAWS in-house inspectors and also served as substitutes on weekends, holidays and when SAWS inspectors went on vacation.